Variante di Zogno (BG)

Project Name

Variante di Zogno (BG)

Year

2020

Main Client

Anas/Aria Lombardia

Our Client

Collini Lavori Spa

Category

Reinforced Soil Slopes

Location

IT

About this Project

In November 2020, Collini Lavori Spa had to install a retaining wall with micropiles, as part of the permanent works required to stabilise the slope cut and safely widening the new road. Due challenging site topography, remote access and tight space, a temporary wall was required to allow micropiles operations.

Tailor Engineering provided temporary works design services for a geosynthetic reinforced soil wall capable to support the piling rig during access and installation.

Variable geological stratification, complex geometry with steep crest and toe slopes and heavy loading machine were some of the challenges Tailors’ had to consider. The temporary wall was designed as a customized solution with a reduced footprint to achieve an overall face angle of 79 degrees, and a maximum height of 6.2 m.

Contact Us

Book a consultation

Schedule a meeting with our team to discuss your project requirements and the scope of work.

Send us a Message

Search Tailor Engineering

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Read our Privacy Policy here.